6 km of drinking water mains, 6 km of sewer pipes and 450 connections with meter boxes, improving water supply and sewer network performance.
This project was carried out by our own crews with our own equipment. It is an example of our work in:
- Client
- SMGEAG
- Location
- Petit-Canal
- Trade
- Water networks
- Duration
- 8 months
- Amount
- €6,275,044
- Status
- Delivered in 2025